Machine is in place in Varberg

The whole machine is now in place in Varberg. There are many parts and there is a lot of electricity that requires installation and it is now only part left before the machine is ready. Running time is long and the production will certainly be modified several times during the running time. Test runs have begun on a good performance, and we are trying to increase the speed step by step to all components are correctly calibrated and are in production. An early stage of prototypes have been made. Packline is still in the planning stages. SAT-test is planned to be implemented on November 15, and we hope to be able to produce “dummy” series in early December.